Battle: Dar es Salaam vs Nairobi

Battle: Dar es Salaam vs Nairobi

Meanwhile

Screenshot_20210713-182425_YouTube.jpg


Screenshot_20210714-155428_Gallery.jpg


Screenshot_20210714-155452_Gallery.jpg


Screenshot_20210714-155438_Gallery.jpg


Screenshot_20210714-155505_Gallery.jpg


Screenshot_20210714-155522_Gallery.jpg


Screenshot_20210714-155533_Gallery.jpg


Screenshot_20210714-155545_Gallery.jpg


Screenshot_20210714-155648_Gallery.jpg


Screenshot_20210714-155719_Gallery.jpg
 
Tanzanian will forever remain an idiot, who cheated you that the biggest dam in East Africa is JNHP? Hiyo dam yenu hata thwake dam imeishinda in terms of water holding capacity.

Beloew is thwake dam under construction.

View attachment 1897957

View attachment 1897958

View attachment 1897960

View attachment 1897961

View attachment 1897962

View attachment 1897963

View attachment 1897964

View attachment 1897965

View attachment 1897966

View attachment 1897968

Punguza kutumia miraa mzee nend kafanye research vizuri ndio uje ubwabwaje
 
Tanzanian will forever remain an idiot, who cheated you that the biggest dam in East Africa is JNHP? Hiyo dam yenu hata thwake dam imeishinda in terms of water holding capacity.

Beloew is thwake dam under construction.

View attachment 1897957

View attachment 1897958

View attachment 1897960

View attachment 1897961

View attachment 1897962

View attachment 1897963

View attachment 1897964

View attachment 1897965

View attachment 1897966

View attachment 1897968
The only fool that i know in this forum is bwana mipesa...
Ivi huo uchafu unataka kulinganisha na Nyerere mda wote ulikuwa unatafuta pakujifichia
 
hiki mbona kidimbwi? Mtazalisha umeme kiasi gani? Ati 20 MW ? Ni josho ama?

c1L_mYI4dBy4UVzjwFHKYRsFy3yZwgwcJtKdgHJd9sGX6a3R1zDHSTUqx-VuABYEAt2E4Qgo0htUeVL0iaSFOD59OPSFcBBVgOuk3sUgVQ=s1200



Na ni fedha za AfDB...


Thwake Dam inches closer to reality


The multipurpose dam project is currently 32 per cent complete.

Author-80x80.png

Updated
January 1, 2021
By
Miriam Nkirote


Thwake-Dam-Bridge.jpg
Ongoing works at Thwake Dam. PHOTO | COURTESY

Construction is well underway on the Sh82 billion Thwake Dam, which is coming up on the border of Kitui and Makueni, with the contractor working to recover the time lost due to the coronavirus pandemic.

According to Apopo Lentana of China Ghezouba Company, the project’s main contractor, engineers are undertaking major works at the site including establishing two giant tunnels to divert Athi River flow for excavation works at the river bed.

“We are currently at 32 percent and we will compensate on time lost during this period of the pandemic….By the end of this year, we will have completed the tunnels.” Lentana said.

The project should be at 37 per cent were it not for reduction of the number of workers on site to 700 down from 1,200 in line with the Ministry of Health guidelines to contain the spread of the coronavirus.

One of the tunnel, which will be 700 metres long on completion, is currently at 280 metres. The two tunnels will be used as substitute water ways where Athi River will change course before later joining the original path to the Indian Ocean.

“Once the river is diverted, there will be building of rock field dam wall that will be 87 meters high then making of main and minor spillways for excess water flow.” Lentana said.

Jointly funded by the Government of Kenya and the African Development Bank (AfBD), the project will be implemented in four phases at a cost of Sh81.89 billion.

Phase one, which is underway, involves construction of an 87m high dam wall with 688 million cubic metre storage capacity, and preliminary works for the implementation of the subsequent three phases.

The second phase of Thwake Dam project will involve installation of a hydropower generation plant while phase three comprises the installation of water supply, sanitation, and waste water infrastructure.

The fourth phase will involve the development of the irrigation component.

Through budgetary allocations to the respective ministry, the government will invest Sh59.95 billion into the project while AfBD will fork out Sh21.94 billion.

Thwake Dam will provide water for domestic, irrigation, hydropower as well as industrial activities in the beneficiary counties.

It will mainly serve Makueni County as well as certain parts of Kitui County.

In March 2019, then Auditor-General Edward Ouko warned that the project may never be completed because the government was yet to negotiate or secure funding for the last three phases of the project.

He said that although the AfDB and the government had approved Sh42 billion funding for phase one of the project, the remaining phases with a budget of Sh40 billion were yet to be planned for.

“The (government) is yet to negotiate or look for financiers for the remaining phases. Consequently, it is not clear how the three phases will be financed to project completion,” Mr Ouko said in a qualified audit opinion on the financials of phase one of the project.

Ukisikia ucgafu ndio huo sasa...
 
hiki mbona kidimbwi? Mtazalisha umeme kiasi gani? Ati 20 MW ? Ni josho ama?

c1L_mYI4dBy4UVzjwFHKYRsFy3yZwgwcJtKdgHJd9sGX6a3R1zDHSTUqx-VuABYEAt2E4Qgo0htUeVL0iaSFOD59OPSFcBBVgOuk3sUgVQ=s1200



Na ni fedha za AfDB... 🙆‍♂️ 🙆‍♂️ 🤭🤭🤭🤷‍♂️🤷‍♂️🤷‍♂️


Thwake Dam inches closer to reality


The multipurpose dam project is currently 32 per cent complete.

Author-80x80.png

Updated
January 1, 2021
By
Miriam Nkirote


Thwake-Dam-Bridge.jpg
Ongoing works at Thwake Dam. PHOTO | COURTESY

Construction is well underway on the Sh82 billion Thwake Dam, which is coming up on the border of Kitui and Makueni, with the contractor working to recover the time lost due to the coronavirus pandemic.

According to Apopo Lentana of China Ghezouba Company, the project’s main contractor, engineers are undertaking major works at the site including establishing two giant tunnels to divert Athi River flow for excavation works at the river bed.

“We are currently at 32 percent and we will compensate on time lost during this period of the pandemic….By the end of this year, we will have completed the tunnels.” Lentana said.

The project should be at 37 per cent were it not for reduction of the number of workers on site to 700 down from 1,200 in line with the Ministry of Health guidelines to contain the spread of the coronavirus.

One of the tunnel, which will be 700 metres long on completion, is currently at 280 metres. The two tunnels will be used as substitute water ways where Athi River will change course before later joining the original path to the Indian Ocean.

“Once the river is diverted, there will be building of rock field dam wall that will be 87 meters high then making of main and minor spillways for excess water flow.” Lentana said.

Jointly funded by the Government of Kenya and the African Development Bank (AfBD), the project will be implemented in four phases at a cost of Sh81.89 billion.

Phase one, which is underway, involves construction of an 87m high dam wall with 688 million cubic metre storage capacity, and preliminary works for the implementation of the subsequent three phases.

The second phase of Thwake Dam project will involve installation of a hydropower generation plant while phase three comprises the installation of water supply, sanitation, and waste water infrastructure.

The fourth phase will involve the development of the irrigation component.

Through budgetary allocations to the respective ministry, the government will invest Sh59.95 billion into the project while AfBD will fork out Sh21.94 billion.

Thwake Dam will provide water for domestic, irrigation, hydropower as well as industrial activities in the beneficiary counties.

It will mainly serve Makueni County as well as certain parts of Kitui County.

In March 2019, then Auditor-General Edward Ouko warned that the project may never be completed because the government was yet to negotiate or secure funding for the last three phases of the project.

He said that although the AfDB and the government had approved Sh42 billion funding for phase one of the project, the remaining phases with a budget of Sh40 billion were yet to be planned for.

“The (government) is yet to negotiate or look for financiers for the remaining phases. Consequently, it is not clear how the three phases will be financed to project completion,” Mr Ouko said in a qualified audit opinion on the financials of phase one of the project.

Wakenya bila data wanakuingiza chaka
 
Tanzanian will forever remain an idiot, who cheated you that the biggest dam in East Africa is JNHP? Hiyo dam yenu hata thwake dam imeishinda in terms of water holding capacity.

Beloew is thwake dam under construction.

View attachment 1897957

View attachment 1897958

View attachment 1897960

View attachment 1897961

View attachment 1897962

View attachment 1897963

View attachment 1897964

View attachment 1897965

View attachment 1897966

View attachment 1897968
Wakenya wenzako wameogopa hata kukupa like mana jana waliyaona vzr hayo makuta ya Babeli wakachanganyikiwa mpk leo hawaelewi kama ndio Tz waliyoambiwa na bibi zao au

Shida ni kwamba wewe huwa bandle linakusumbua sana, hukuona
 
Back
Top Bottom