Part of Terminal-III rooftop collapses

Part of Terminal-III rooftop collapses

Dingswayo

JF-Expert Member
Joined
May 26, 2009
Posts
4,019
Reaction score
2,930
Hitch caused by `poor`construction material

Part of the rooftop of Terminal-III building, which is still under construction at Julius Nyerere International Airport (JNIA) in Dar es Salaam, crumpled last week, posing a security threat to the workers on site.

It was the first incident of its kind since the two-phased project kicked off in January, last year, but Director General of the Tanzania Airports Authority (TAA), Eng. Suleiman Suleiman, described it as "too minor to deserve public attention."

However, he has reportedly given the contractor, Bam International Construction Company, a two-week ultimatum to release a report over the 6-metre affected area, amid fears that the crash might entirely destroy the 75,000 square-metre terminal structure.

Pending results from a probe team while the non-affected portion has already been inspected by a team of engineers as required by the terms of contract, Engineer Suleiman suspected faulty bolts as the cause of the collapse, noting that the detected hitches would be communicated back to the manufacturers and suppliers.

"Usually, samples from all imported building materials are tested to ensure they are up to required standards. It might be that the failed bolts were not tested since not all materials are taken to the testing site," he said.

"It is up to the contractors to take appropriate measures against the manufacturers and suppliers of the substandard construction material.

What we need is the handover of a perfectly accomplished project according to the terms of the contract," said the TAA chief in response to a question as to what would happen if the construction materials were of poor quality.

"That's why the contractor is paid only after completion of the project and with the approval of construction experts," he noted, adding that the terms also required the contractor to remain in the country a year after handing over the project.

The Guardian on Sunday had responded to a tip-off by a concerned worker who, like others, feared for his life following the collapse in a situation they alleged was short of social security as they even had no insurance cover.

But it was later established that Bam had adhered to all basic safety standards, including provision of safety gear, and placement of instruction banners across the site.

"They don't have to be worried for their safety. The working environment is safe, information well-communicated and the situation closely monitored," said the TAA boss, while pointing at a temporary Safety Unit building and a stand-by ambulance at the site.

Bam officials declined to comment as they directed the reporter to TAA for any information.

Terminal 3, a 75,000-square-metre complex five times bigger than Terminal-2, will be served by 40 counters, equipped with 18 air bridges and designed to dock gigantic A380 Airbus planes.

Completion of the ambitious project will see JNIA playing the role of Tanzania's main international gateway as passenger annual turn out will be increased to 6 million.

The construction of Terminal 3 is done in two phases including the Sh293bn phase one scheduled for completion next year to handle 3.5 million passengers annually, and the Sh225bn phase two scheduled to accommodate 2.5 million travelers on its completion in 2017.

The project is in place thanks to the Dutch-government guaranteed loan from HSBC Bank through Export Credit Agency and 15 per cent financial involvement from the local CRDB Bank.


SOURCE: GUARDIAN ON SUNDAY

 
but Director General of the Tanzania Airports Authority (TAA), Eng. Suleiman Suleiman, described it as "too minor to deserve public attention."

Teh teh
 
Only in Tanzania

It can happen anywhere. This is what happened in France, Charles de Gaulle International airport May 23, 2004


9k=







images
 
We cautioned last year about the possibility of substandard due to some funds being diverted to ccm and its officials and now is happening

And there is still more to come. In Nigeria they finished all the reserve but yet they failed the election. The most likely situation is going to happen
 
And there is still more to come. In Nigeria they finished all the reserve but yet they failed the election. The most likely situation is going to happen

✌ that's why we say enough is enough
 
Ufisadi utaimaliza Tanzania.
Hapo sio salama tena.
Kama kisehemu kimeanguka kwasababu ya vifaa duni basi tutegemee jengo zima kuwa chini ya kiwango.
 
Jengo linaanguka kabla hata halijapata mtikisiko wa ndege kubwa km Airbus, cjui itakuwaje zikianza kutua
 
Back
Top Bottom