THE GOVERNMENT SHOULD REVOKE THIS CONTRACT
Agreement may be terminated at any time:
(a) By either part, by way of notice of termination on the basis of default,
(b) by either part, through proof of force majeure pursuant to clause
(c) by either part by way of notice of termination for the change of law
(d) by either part by way of notice of termination for expropriation
(e) by agreement between the parties
Circumstance which constitute default by CONCESSIONAIRE
a. If at any time the concession payment, or any portion thereof, payable by the CONCESSIONAIRE is in arrears and unpaid for three month. (IMEVUNJWA)
b. If CONCESSIONAIRE cease conducting Railway operations or providing railway services r railway passenger services for period of 14 days or more (IMEVUNJWA KAZIUA LOCOMOTIVES NA MABEHEWA YA KUKODI YASITEMBEE NA KUKAIDI AMRI YA WAZIRI)
c. If at any time material reduction of services takes place. (IMEVUNJWA. HUDUMA ZIKO CHINI KWA ASILIMIA 100 TOKA AKABIDHIWE SHIRIKA HILI 2007 ZILIBEBWA WASTANI TANI 100,000 KWA MWEZI SASA NI TANI 40,000 KWA MWEZI)
d.
e. CONCESSIONAIRE declared insolvent or bankrupt by court of competent jurisdiction. (IMEVUNJWA . WAMEFULIA MSHAHARA WANALIPIWA NA SERIKALI NA KAMPUNI ZA MAFUTA ZIMEKOMA KUWAPA MAFUTA WANANUNUA KWA GELENI)
f. If CONCESSIONAIRE assigns the agreement to any other entity without approval of RAHCO (HII BADO)
g. If CONCESSIONAIRE fails to meet standards and Minimum requirements of schedule 4 (IMEVUNJWA TENA SANA HAWAJAFANYA LOLOTE KUHUSU NJIA YA RELI . HATA ZILE dollA 14 MIL ZA IFC HAZIJULIKANI ZIMEFANYA NINI?)
Consequences of Default
i RAHCO is entitled to claim against CONCESSIONAIRE and Bond provider as liquidated damages as per the performance bond (schedule 12)
ii RAHCO to purchase all moveable assets at a price lesser than the then residual value of fair Market value. RAHCO have the right to use these assets pending settlement agreement or arbitration of the exact price.
iii CONCESSIONAIRE is prohibited from claiming indemnity from RAHCO
FORCE MAJEURE
In case the termination is caused by Force Majeure CONCESSIONAIRE will have no claim against RAHCO.
Hawa jamaa wameipa Serikali Notice ya miezi miwili kuishia NOV 9 kwa wataondoka kwa vile
Serikali haijalipia loco walizokodisha 10Bil
Sumatra imezuia mabehewa yao ambayo mabovu na chini ya kiwango
Migogoro ya wafanyakazi isiyoisha
WANAZUONI MSAIDIENI KAWAMBWA