Exclusive: TANESCO's Audited Report from PPRA

Kuna maswali mengi sana kuhusiana na Richmond kwenye hii document. Kwanzia page ya 40. Very very Interesting. Sijui ndio maana lowasa akashtuka?
 
Tender
PC/10/2006 for Emergency Power Supply from rental Gas Based Generating Plant of 100MW


Summary of issues in the tender

• Procurement plan was not prepared for the tender – tender treated as emergency procurement but advertised internationally

• There was no cost estimates for the bid

• The cost of administering the tender process was not adequately documented

• No evidence that tender notices and bid documents were approved by the tender board

• 26 companies bought the tender documents but only 8 tendered

• Bid opening was initially 13.03.2006 but was later extended to 20.03.2006 on request from some of the bidders

• Time lapse between bid opening to contract award, 95 days

• Bid validity was up to 19 May 2006, 60 days from the bid submission day

• There was no request to extend bid validity, contract was signed 23 June 2006 – 35days after bid valid deadline

• Evaluation team was not appointed by CEO but by TB

• Personal covenant forms/bid declaration forms were not signed by evaluation personnel

• 12 members were appointed by the TB to carry out evaluation for the submitted tenders

• The bid evaluation process was not done strictly following the criteria that were stated in the bid documents e.g. bid security requirement was waived, revision of weighted scores to 60% technical and 40% commercial. The evaluation was to be redone with the second one with substantial flexing of the evaluation criteria

• Tender Board does not act very independently, several interferences from the Tanesco Board of Directors

• Tanesco cancelled the tender since all the 8 firms were not responsible to the terms of reference and the government was already interfering with the procedures

• Ministry of Energy and Minerals recalled bid documents submitted by all the 8 bidders from Tanesco so that it processed them itself – the process which eventually came up with Richmond Development Company LLC. The Tanesco evaluation process, before it was abandoned, had indicated Renco SPA of Italy and Real Energy of UK as more relatively responsive to the bid requirements than Richmond Development Company LLC respectively.

• Negotiations with Richmond was carried out under a Government Negotiation Team, which was appointed by the ministry

• Tanesco Board was ordered by the Ministry of Energy and Minerals to sign the contract despite Tanesco initial resistance especially after the process that brought the winner was handled outside Tanesco procurement process

• Contract between Tanesco and Richmond Development Company was signed in strange circumstances, at night and at the ministry of Minerals and Energy with some contractual issues protecting the client having been ignored as there was no room for Tanesco to review the draft contract (the Company Secretary does not know who drafted the contract) e.g. No performance bond, etc. the power rental agreement is for two years at $0.0499/kwh of 100MW i.e. the capacity price is 34.60565 US$ per KW per month, calculated as, 0.0499 (US$/kWh)x24(hrs)x365(days) x 95% (availability factor)/ month

• Contract between RDC and Tanesco did not provide for re-assignment of the contract to Dowans but subcontracting arrangement however political influence forced Tanesco to waiver from principles of the contract

• Indemnification agreement was reached requiring Dowans Holdings SA to take all liabilities of Richmond Development Company LLC

• Since Richmond failed to honour the agreement, liquidated damages started to apply beginning 2nd February 2007 at US$ 10,000 per day, the official commercial operating date (150 days since the letter of Credit was issued). There is no agreement between the parties as to how the amount would be claimed from Dowans Holdings.

• Performance guarantee was withdrawn from the requirements list by the Government during the negotiation period with Richmond Development Company LLC against Tanesco wishes of having it stay.

• Advance payment of US$ 15million has already been paid to Dowans and all the plants to generate 100MW have already arrived and are now in the process of being installed at Ubungo.

• There are proposals now that the power plants be sold to the Government after the 2 year lease period
 
Nilikuwa najiuliza kwa nini TANESCO iko taabani, sasa nina jibu?

Sasa, Wataalamu NetGroup walikuwa wakifanya nini kipindi hicho, maana complication zote ninauhakika waliziweka wao, Wabongo najua wazuri sana kuweka at least process and procedures kwenye makampuni?

Mimi Nashukuru kwa Report, maana ni Mwanzo Mzuri, ukijua tatizo ndio nusu ya kulitatua....
 
Tanzania yangu ... inaliwa na wajanja wachache wenye meno huku waksha hoi wakizidi kuliwa na kuumia. Kweli mwenye nacho huongezewa na asiye nacho huporwa hata kile kidogo alicho nacho!
 
Wazungu wa Net Group walisema, "Hivi Watanzania muna akili kweli?" kauli hiyo ikamponza Mzungu wa watu akaondolewa nchini. Hebu fikiria, mzungu anatetea maslahi yenu munamtimua wakati ule akiwa anaharibu mulimlinda kwa FFU. kazi kwelikweli
 
Anytime bro. Karibu

Ahsante sana invicible. Nilikuwa sioni muziki basi nikaenda kwenye search nikaingiza ASAP mambo yakajipa. Sasa itakuwa vizuri kama tutaupata muziki wa Mkapa na Yona kujipatia Kiwira na Muziki kati ya Mkapa/Yona na Tanesco.
 
patamu hapo.... Naendela kusoma hii braking news, sababu when the news brake out we brake in.

Duh...!! kaaazi kweli kweli, lakini tutafika tu. Naona kamgao ka kasungura ka Lowasa kaendela kwa mwendo mdundo. Ka sungura haka naona kameombewa dua, maana hakaishi na mgao bado unaendela......nani alisema lazima iwe ng'ombe!!!?.
 
Jamani PCCB wanaweza kutuambia ule upuuzi wao wa kuisafisha RDC waliupata wapi? Sasa hii si aibu kubwa sana kwa huyu bwana Hosea na timu yake? Kweli hii nchi kazi bado ipo! Kila mahali pameoza. I wish kama kunauwezekano Invicible tupatie na hiyo ripoti ya PCCB pia tuione.
 
Hahaha, watu mnanifurahisha. Ina maana mshaisoma yote hii kitu? Mbona wengine huwa wanadondoka sahihi mambo flani bila kuumiza vichwa?

Yangu mie macho
Invisible

Hii kitu niliisoma ndani ya dakika 80, nilibebaba laptop yangu na kujifungia board room, sikutaka kusubiri, nilipo fika page ya 30 nilipata kizungu zungu

kumbe ile tabia ya kukimbizana na mikata kwenye mikoba ya haikuanzia buzwagi

Contract between Tanesco and Richmond Development Company was signed in strange circumstances, at night and at the ministry of Minerals and Energy with some contractual issues protecting the client having been ignored as there was no room for Tanesco to review the draft contract (the Company Secretary does not know who drafted the contract) e.g. No performance bond, etc. the power rental agreement is for two years at $0.0499/kwh of 100MW i.e. the capacity price is 34.60565 US$ per KW per month, calculated as, 0.0499 (US$/kWh)x24(hrs)x365(days) x 95% (availability factor)/ month

• Contract between RDC and Tanesco did not provide for re-assignment of the contract to Dowans but subcontracting arrangement however political influence forced Tanesco to waiver from principles of the contract

• Indemnification agreement was reached requiring Dowans Holdings SA to take all liabilities of Richmond Development Company LLC

• Since Richmond failed to honour the agreement, liquidated damages started to apply beginning 2nd February 2007 at US$ 10,000 per day, the official commercial operating date (150 days since the letter of Credit was issued). There is no agreement between the parties as to how the amount would be claimed from Dowans Holdings.

• Performance guarantee was withdrawn from the requirements list by the Government during the negotiation period with Richmond Development Company LLC against Tanesco wishes of having it stay.

• Advance payment of US$ 15million has already been paid to Dowans and all the plants to generate"

Kazi kweli kweli, siku yao inakuja tena yaja upesi..........siku hiyo fisadi ataitwa fisidi
 
Hii kitu nimesha isoma yote, it took me the whole day kuangalia, from excutive summary to last dot.

Wakubwa I hope mtamaliza sasa tuanze kumchambua huyu sungura.
 
Maumivu Haya ni Makali,Ewe Mola Wetu Tuhurumie!

KNKCU,

Pole sana mkuu. Long time sijakuona online na mkuu Yebo Yebo. Mlikuwa mkililia kupata madude kama haya na sasa mnayapata na mtu unajikuta unachoka pale unapoujua ukweli.

Inshallah, Mwenyezi Mungu atasaidia na mambo yataenda sawa endapo watanzania tutasaidia katika kutoa mapendekezo juu ya namna ya kuendesha nchi yetu tuipendayo - Tanzania.

Karibu
 
KNKCU,

Pole sana mkuu. Long time sijakuona online na mkuu Yebo Yebo. Mlikuwa mkililia kupata madude kama haya na sasa mnayapata na mtu unajikuta unachoka pale unapoujua ukweli.

Inshallah, Mwenyezi Mungu atasaidia na mambo yataenda sawa endapo watanzania tutasaidia katika kutoa mapendekezo juu ya namna ya kuendesha nchi yetu tuipendayo - Tanzania.

Karibu
Nashukuru!
Dunia na Tabu Zake ndiyo inaninyima muda Lakini tunaomba Uzima Ipo siku Nchi itarudi mikononi mwa Viongozi wa Nyonge na si kwa Viongozi wa Vibepari uchwara. Na Masilahi ya Taifa ndiyo yatatawala maamuzi na Fikra zetu!
 
Back
Top Bottom