When you do things for clout

Nivlark

JF-Expert Member
Jul 19, 2013
385
293
Addis- Djibouti Standard Gauge Railway line suffers a myriad of operational and financial difficulties that hamper its efficiency and reliability, a recent study says. Other sources complain of frequent stoppages, some taking as long as two weeks to solve.

Power outages, the study shows, is a major problem affecting not only its reliability but also its safety. The study, “Sino-Ethiopia evolving partnership along Addis Ababa-Djibouti, railway economic belt ” identified power outages, poor maintenance, thefts, lack of funds, and accidents as the leading problems.

Frequent power cuts disrupted operations including rescue, slope stopping, regression, and are a very serious risk to the train’s safety. The study found out that train lost 48,000 hours of operation arising from more than 8000 power outages since its inception in 2016.
Sixty percent of these interruptions lasted up to three hours to rectify; three percent lasted more than a day than, while1.3 percent lasted longer. This puts the $5 billion investment at stake.

On safety of the train and its cargo, the study, quoted by a local newspaper, The Ethiopian Reporter established that there were 573 incidents recorded up to October 31, 2019. These include; theft of basic equipment such as rail fastenings, poor maintenance and lack of funds. These, says the study, pose a serious risk of derailment and accidents.

It refers to April 2019 for instance, when a 53-wagon train to Djibouti derailed on a flooded and muddy line in East Shewa Zone in the Oromia. This incident cost an estimated 200 million to 300 million birr(US$6.22 to 9.33 Million) due to the suspension of its operations for several days.

Other accident-related risks include collision with livestock and theft of critical spare parts on the railway line such as fasteners. In addition to delays, they pose a major derailment risk. These risks combined have forced the operators to reduce its travel speed from the projected 120 Kilometres per hour to 50 kilometers.

Compounding the problems, the study found, is poor maintenance of rolling stock. It found that owing to Lack of maintenance facilities, including spare parts, a significant number of locomotives are defective. For instance eight of the 35 electric engines and two of the Six diesel engines, have serious faults. The 502 freight wagons, the study found, are operating with serious defects such as bearing oil seepage and, air leakage in the braking system, that jeopardize the trains’ safety.

The challenges facing the Addis - Djibouti line is a wake-up call for African governments that are currently, considering electric trains. They must avoid placing the "Cart before the Horse" i.e they should not invest in the electric train if they do not have sufficient idle power generating capacity. Experts say that an electric train requires 1000MW to run efficiently. Ethiopia’s known power generating capacity is 4500MW. This does not leave it with sufficient idle capacity to run an electric train.

Further, high-speed Railway lines need to be separated from other forms of users, such as animals, and motor vehicles. This is why they are elevated. In the Case of the Addis Ababa- Djibouti Line, there are no such protections for it has level crossing rather than bridges.

That is why thieves and other malicious characters can steal the Line Fastenings.
source
Blogger: User Profile: East Africa Economics Report
 
Hawa ndo walikua wanatumika kama mfano kuikejeli kenya ati treni ya umeme

Sasa hivi kenya imebeba wasafiri mara kumi na nne zaidi ya sgr ya Ethiopia tangu ianze na kusafirisha mzigo kubwa zaidi

Watz wanafaa kuchukua mfano huwezi kujifanya kutumia treni za umeme wakati viwanda na wananchi hawapati umeme wa kutosha kwa bei nafuu
 
Hawa ndo walikua wanatumika kama mfano kuikejeli kenya ati treni ya umeme

Sasa hivi kenya imebeba wasafiri mara kumi na nne zaidi ya sgr ya Ethiopia tangu ianze na kusafirisha mzigo kubwa zaidi

Watz wanafaa kuchukua mfano huwezi kujifanya kutumia treni za umeme wakati viwanda na wananchi hawapati umeme wa kutosha kwa bei nafuu
Tulia buda acha kujipa ma "feeling" ya ajabu,hii ni TZ na hiyo ni Ethiopia, unajua sasa tunazalisha umeme kiasi gani?unajua sisi tumejipanga kwa kiasi gani?Ethiopia na Kenya mmewekwa kwenye kapu moja na wa wachina,so,usiitaje TZ kwa kujifariji.subiri yetu ikamilike ndo muongee.Tunajua inawauma baada ya yetu kuizidi ya kwenu.
 
This is why Kenya chose to:
i) Build a whole new track different from the old line ie The whole Kenyan sgr is a greenfield project.
ii) Put fences along the wayleave and to elevate the track in the parks and above roads to avoid animal collisions.
iii)Build new roads along the track to be used by maintenance teams.
iv) Actively train engineers and sponsored students to learn train maintenance and railway technology in chinese universities including internships at CRRC where the trains are built.
v) Use diesel locomotives to allow for double stack wagons ie. electric lines can not do double stack wagons due to the overhead wiring.
vi) Invest first in a professional workforce by technology transfer from the chinese to the Kenyan employees.

Result has been:
i)Kenyan sgr trains are always on time.
ii) No accidents involving animals and humans since the track is fenced all along the route and elevated inside the parks complete with noise dampening equipment to avoid stressing animals (Requirement by the court after environmentalists won a case against GOK).
iii) excellent safety and punctuality record with 0 accidents despite moving millions of passengers annually and only 2 recorded damage to cargo which has prompted insurance companies to reduce charges on cargo but increase charges on covering truck hauled cargo.
iv) About 14,000 trains operated in 1000 days covering a total distance of 6.368 million kilometers without any safety accident.
 
This is why Kenya chose to:
i) Build a whole new track different from the old line ie The whole Kenyan sgr is a greenfield project.
ii) Put fences along the wayleave and to elevate the track in the parks and above roads to avoid animal collisions.
iii)Build new roads along the track to be used by maintenance teams.
iv) Actively train engineers and sponsored students to learn train maintenance and railway technology in chinese universities including internships at CRRC where the trains are built.
v) Use diesel locomotives to allow for double stack wagons ie. electric lines can not do double stack wagons due to the overhead wiring.
vi) Invest first in a professional workforce by technology transfer from the chinese to the Kenyan employees.

Result has been:
i)Kenyan sgr trains are always on time.
ii) No accidents involving animals and humans since the track is fenced all along the route and elevated inside the parks complete with noise dampening equipment to avoid stressing animals (Requirement by the court after environmentalists won a case against GOK).
iii) excellent safety and punctuality record with 0 accidents despite moving millions of passengers annually and only 2 recorded damage to cargo which has prompted insurance companies to reduce charges on cargo but increase charges on covering truck hauled cargo.
iv) About 14,000 trains operated in 1000 days covering a total distance of 6.368 million kilometers without any safety accident.
Nice one
 
Niliambia Geza Ulole kuwa hii reli yao ya umeme ni white elephant kwa sababu hawana umeme, akaniambia wanajenga Nyerere hydroelectric dam. Dam yenyewe iko 25% complete. Watapata shida sana
 
Niliambia Geza Ulole kuwa hii reli yao ya umeme ni white elephant kwa sababu hawana umeme, akaniambia wanajenga Nyerere hydroelectric dam. Dam yenyewe iko 25% complete. Watapata shida sana
Kaka umeme wa kuendesha reli tunao...kitu kingine SGR ya Tz hakuna mahali inapishana na magari kote wamezingatia ilo...iko na madaraja mia mbili phase one..
 
Tanzania SGR will suffer the fate like Ethiopia because the trains have no way leave but rather level crossing (also called a grade crossing, railway crossing, or a railroad crossing). This means that the grades (the road and the track) are not separated by using a bridge or a tunnel. Secondly, i doubt the demand for train services to the west of the country given than majority of Tanzanians live along the coast, southern part of the country and along the northern border with Kenya.

The train is headed west to a sparsely populated part of the country. Thirdly, Power capacity in Tz to power the trains is lacking remember the train power is dedicated power and is not shared. If this train will ever move and assuming they sort our power issues, it will be once a day therefore economically nonviable business. Tanzania built their SGR not because there was a demand but because it wanted to compete with Kenya.
 
Tanzania SGR will suffer the fate like Ethiopia because the trains have no way leave but rather level crossing (also called a grade crossing, railway crossing, or a railroad crossing). This means that the grades (the road and the track) are not separated by using a bridge or a tunnel. Secondly, i doubt the demand for train services to the west of the country given than majority of Tanzanians live along the coast, southern part of the country and along the northern border with Kenya.

The train is headed west to a sparsely populated part of the country. Thirdly, Power capacity in Tz to power the trains is lacking remember the train power is dedicated power and is not shared. If this train will ever move and assuming they sort our power issues, it will be once a day therefore economically nonviable business. Tanzania built their SGR not because there was a demand but because it wanted to compete with Kenya.
Kwa akili yako tu ya kawaida na nyie mna SGR Au matope
 
Kama Corona TZ wamemaliza nchi mzima, wakati nchi kama USA na UK bado zinapigana, reli watashindwa kweli..
CCM hoiyee Magufuli HOIYEE
 
Duh... tuliona mbali sana kwa SGR yetu.

Halafu Tz na mbwembwe zote zile mpaka leo kale kasafu kao ka Dar-Moro sijui wamekaficha wapi, maana walisema katawashwa mwaka jana Novemba.
 
Duh... tuliona mbali sana kwa SGR yetu.
Halafu Tz na mbwembwe zote zile mpaka leo kale kasafu kao ka Dar-Moro sijui wamekaficha wapi, maana walisema katawashwa mwaka jana Novemba....
"They are still ahead of us", Magufuli can declare it a success no matter what failures, anybody who says anything contrary to that will be arrested.
 
The way they've handled this corona pandemic has exposed their underbelly, they have a serious problem.
it has exposed his insecurities , the guy has the emotional stability of a rat in a burning house
 
Mzee una confidence Kama una uhakika!! Kusini mwa Tz Kuna population gani!!!

FYI kanda ya ziwa ndiyo inaongoza kuwa na watu wengi, ukiondoa pwani ya Dar.

Ungetumia akili kidogo kwa kuangalia jiji kubwa zaidi Tz after Dar ni Mwanza. Ata GDP inachangiwa zaidi na kanda ya ziwa baada ya Dar.

Usisahau pia Train itapita Dodoma the Capital and most developing City in Tz kwa Sasa.
Tanzania SGR will suffer the fate like Ethiopia because the trains have no way leave but rather level crossing (also called a grade crossing, railway crossing, or a railroad crossing). This means that the grades (the road and the track) are not separated by using a bridge or a tunnel. Secondly, i doubt the demand for train services to the west of the country given than majority of Tanzanians live along the coast, southern part of the country and along the northern border with Kenya. The train is headed west to a sparsely populated part of the country. Thirdly, Power capacity in Tz to power the trains is lacking remember the train power is dedicated power and is not shared. If this train will ever move and assuming they sort our power issues, it will be once a day therefore economically nonviable business. Tanzania built their SGR not because there was a demand but because it wanted to compete with Kenya.
 
Ethiopia wana 4500MW za umeme ila kuendesha treni ya umeme imekuwa kizungumkuti. Umeme umepotea na ukakwamisha shughuli za treni mara 8,000 tangu 2016! Treni ikikwama inachukua hadi wiki moja kufanya repairs, hasara ya hitilafu ya siku kadhaa, $9.63Million!
 
Back
Top Bottom