Comparison between construction of Kimwarer dam and hydropower project and Nyerere dam in Rufiji Hydropower project

Geza Ulole

JF-Expert Member
Oct 31, 2009
59,022
78,984
Rufiji Hydropower Project

The 2,100MW Rufiji hydropower project is being built on the Rufiji River in Stielger’s Gorge, Selous Game Reserve of Tanzania. With a gross output of 5,920GWh, the plant will more than double the country’s power generation capacity, upon commissioning.

Construction on the £2.24bn ($2.9bn) project was officially started in June 2019, while commissioning is expected in 2022.

Tanzania Electric Supply Company (TANESCO), which is operated by the Ministry of Energy and Mines, is undertaking the project.Tanzania’s federal budget proposal, unveiled in May 2018, earmarked $307m for the project, which accounts for approximately 40% of the country’s total federal budget.

Rufiji hydropower plant make-up

The Rufiji hydropower project will include the construction of a roller compacted concrete (RCC) dam on the Rufiji River. The dam will be 134m-tall and have a storage capacity 34 million cubic metres (Mcm) of water.

PROJECT GALLERY
The reservoir will be 100km-long and 1,350km² in area, while the earth embankment will be 3.7Mcm.

The power house will be above-ground and consist of nine vertical Francis turbines with capacity ranging from 200MW to 300MW each, and power generators with a capacity of 1,200MW each.

The project will also include the construction of spillway drainage with a capacity of 14,000 cubic metres per second (m³/s), two coffer dams, diversion tunnels with a cross section area of 95.4m², and low-level outlets with a capacity of 1,000m³/s.

Infrastructure at Rufiji hydropower project

Power transformers of 235-353MVA each and having a combined capacity of 2,470MVA will be installed. The plant will also include a 400kV switch yard.

Additional infrastructure will include electrical switch gears, protection system, and fire detection system along with auxiliary power supply, DC systems, and cooling and sewage systems.

Construction of 10km-long internal roads, 15km-long residential roads, 350 permanent houses, and 3,000 secondary houses is also part of the project.

Contractors involved

A joint venture of two Egyptian companies, The Arab Contractors and Elsewedy Electric, was awarded the £2.24bn ($2.9bn) engineering, procurement, and construction (EPC) contract for the 2.1GW hydroelectric project in December 2018.

The Arab Contractors holds a 55% share in the contract value, while Elsewedy Electric holds the remaining 45%.

Environmental issues
Rufiji hydropower project has been facing opposition from ecologists as it will occupy 3% or 1,350km² of the 45,000km² of land, which is a part of Selous Game Reserve, a World Heritage Site.

However, during the 41st World Heritage Committee (WHC) session in Poland in July 2017, the delegation from Tanzanian Government asserted the country's firm position to execute the project.
The delegation argued the dam had been in the Government’s agenda since the 1960s, before the Selous Game Reserve was included in the World Heritage List.

Another explanation supporting the project was that the proposed dam occupies a tiny portion of the heritage site, but will benefit the power-starved country in a big way.

Marketing commentary on Tanzanian energy market
Tanzania, the sixth most populous country in the sub-Saharan Africa, has been facing chronic electricity shortage with just 40% of the country’s 59 million population having access to electricity.

The country’s current installed capacity is 1.6GW, which comprises 41.7% hydro, 44.7% natural gas, 12.8% liquid-fuel, and 0.8% biomass-based power generation. As of 2016, the gross electricity generation in Tanzania was estimated to be 6,448GWh, while the per capita consumption was 137kWh/year.

The country’s energy ministry plans to increase the total installed capacity to 5GW by 2021 and to 10GW by 2025.

TANESCO’s generation system comprises mainly of thermal and hydro-based generation, with thermal plants contributing 63% and hydro plants contributing 37%.

Source: NS Energy Business

Capture.PNG
 
Kimwarer Multipurpose Dam Project
  • Employer Keryo Valley Development Authority
  • Country Kenya
  • Sector water and irrigation works, dams
  • Area Elgeyo-Marakwet County
  • Contract value 123,100,000 € (Annual Report 2017)
  • Locality Iten
  • Status ongoing
  • Latitude 0.672615
  • Longitude 35.508039

project description
The project is located in Elgeyo Marakwet County, Soy Location. The Kimwarer Dam and Hydropower Project is located on the Kimwarer River.

Developing the multipurpose project will provide improved food security and improved livelihoods of the communities.
The project will contribute towards alleviating electricity supply deficit in the country, improve food security and will guarantee supply of water for industrial, domestic and irrigation.

Specific objectives of project

1. To produce 20 MW of electricity through development of two HEP along the Kimwarer River.
2. Expansion of area under irrigation by bringing additional 2000 ha of land undercrop farming to support the country’s food security.
3. The production and distribution of potable water for both domestic and livestock consumption.

kithino2.jpg


 
Kimwarer Multipurpose Dam Project
  • Employer Keryo Valley Development Authority
  • Country Kenya
  • Sector water and irrigation works, dams
  • Area Elgeyo-Marakwet County
  • Contract value 123,100,000 € (Annual Report 2017)
  • Locality Iten
  • Status ongoing
  • Latitude 0.672615

  • Longitude 35.508039
project description
The project is located in Elgeyo Marakwet County, Soy Location. The Kimwarer Dam and Hydropower Project is located on the Kimwarer River.

Developing the multipurpose project will provide improved food security and improved livelihoods of the communities.
The project will contribute towards alleviating electricity supply deficit in the country, improve food security and will guarantee supply of water for industrial, domestic and irrigation.
Specific objectives of project

1. To produce 20 MW of electricity through development of two HEP along the Kimwarer River.

2. Expansion of area under irrigation by bringing additional 2000 ha of land undercrop farming to support the country’s food security.

3. The production and distribution of potable water for both domestic and livestock consumption.

kithino2.jpg


Hii ni hatari sana.
 
Back
Top Bottom