Currently (February 2012 )52.52 % of the overall peoject is completed
No Description Progress (As of February 26,2012)Remark
1RCC Dam Excavation100%completed
2RCC Dam Foundation TreatmentprogressingSite clearing ,Dental concreating , leveling concrete and grouting works are in progress
3RCC Dam Concrete Work1.13%RCC placement is commenced on December 18,2012
4Power House Excavation100%Power House excavation from unit 1 to unit 10 is 100% completed
5Plunge Pool Excavation56.5Excavating the Left and Right Abutment and supporting of the rock is in progress
6Power Water WayPower Intake Excavation 100%Completed
Power TunnelsRight Power Tunnel100%
Left Power Tunnel100%
7Surge Shaft ExcavationRight Surge Shaft60.8%Rock support installation is in progress
Left Surge Shaft84.1%
8Penstock ShaftRight Penstock 72.5%Rock support installation is in progress
Left Penstock 22.6%
9Electro Mechanical(EM) works Design 80.3% Installation of PH grounding system,Draft Tube Elbow,Presure measurement tap,PH drainage and dewatering system,Ventilation shaft,embaded pipe is in progress
Manufacturing 19.3%
Delivery 5.5%
Erection2.8%
10Hydraulic Steel Stractue(HSS) works Design 78.8% Installation of Embedded parts for manifold cranes and Draft Tube slide gate and stop log for unit #1 and 2 is in progress
Manufacturing 17.2%
Delivery 2.2%
Erection1.5%

Camps and Site logistic Installation works
Camps for Employer/ Employer Representative, Contractors Expatriate camps and local staff's camps are completed.
Air strip, Clinics, canteens, bars and other social service centers for the staffs are completed.
Site logistic installations such as workshops laboratories, stores, batching plants, crushing plants and other important equipments are in place.


Diversion Tunnels Excavation and lining works of the three diversion tunnels are completed and the dry season flow of Omo River is diverted through the center tunnel on January 20, 2009.
At present, the Omo River flow passes through the three diversion tunnels and the area of the dam foundation and powerhouse is fee of water..

Cofferdams
The concrete wall of the D/S cofferdam has been 100% completed and the rock fill work is 78.5% completed, the contractor has completed installing first and second phase geo-membrane and is preparing to install third phase

RCC Dam Construction
Dam abutment excavation is 100% completed.

Power house area excavation is in progress. Excavation volume has been increased due to shift of PH. As a result 87% of the excavation work is completed relative to the new total area of excavation

Power Waterways

•Power Intake
•The position of the Intake is shifted 250 m left side and 320m right side towards u/s. The quantity of excavation at the new location is estimated to be 227,000 m3. Out of this volume 174,790 m3 is excavated so far. The progress of the work is 81% according to the new volume.
Power Tunnels
• To date the left and right Power Tunnels excavations are approximately 83% and 73.4% completed respectively
Manifolds
Excavation of Branches of the Left and right Manifolds is completed, installation of support structures and wire mesh and shotcrete activities are completed.

Laboratory Works
Second phase of RCC trial mix tests for the main dam is in progress.
RCC trail mix tests on different types and brands of cement are in progress. According to the results Pozolana Portland Cement (PPC) is found to be the best type of cement for RCC Dam construction.

Roads & Bridges

About 135 km long access roads inside the site are constructed.
The Omo downstream Permanent bridge work is 100 % completed and it was opened for Light vehicles traffic on Sep 06, 2009 .
The request for approval of reduction of the right of way of the road from 30 to 20 m is approved by Ethiopian Roads Authority (ERA) in order to reduce the impact of the road. Currently, the consultants has completed the rechecking of the impacts in the 20m corridor and submitted the review of the final resettlement and compensation plan.

Hydromechanical and Electromechanical works
  • Contract for the Electro mechanical and Hydro mechanical works have been signed on May 12, 2010 with DEC (Dongfang Electric International Corporation) of China at a cost of USD 340,727,870 plus ETB 486,627,544 and USD 105,227,709 plus ETB 150,919,919 respectively. The total contract price for the Electro mechanical and Hydro mechanical works in USD is 495,506,200.
  • A tripartite agreement has been made on July15, 2010 among EEPCo, Salini (EPC Contractor) and DEC (Plant Contractor).
  • The contracts for EM and HSS Works are effective as of July 15, 2010.
  • With respect to the submitted drawings/documents, DEC accomplished 28% and 35% design for EM and HSS works respectively.
So far 380 design drawings/documents have been submitted by DEC for review and approval; of the submitted design drawings/document:

    • 262 documents(about 69%) are Returned for Correction(RFC)
    • 54 documents( about 14%) are approved
    • 64 documents under review (about 17%)
  • The manufacturing works of the components of EM and HSS equipments are under progress.
  • The third technical coordination meeting has been conducted from May 23rd to 27th/2011 in Addis Ababa. The meeting has been attended by the representatives of EEPCo, ER, Salini (EPC contractor) and DEC (Plant Contractor).
  • Great emphasis has been given to speed up the design of EM and HSS equipment of the project and ensure the interfacing activities with that of the civil works.
  • In order to speed up the design works, establishment of a team drawn from EEPCo, ER, and EPC contractor is under process. The team will closely work with DEC’s engineers in Chengdu, China.
  • Considering the delays in design of EM & HSS works, EEPCo requested the DEC’s top management support and intervention in order to speed up and ensure the completion of the project as scheduled.
  • As no satisfactory improvement is obtained from DEC’s side, EEPCo invited DEC’s higher level management for a coordination meeting scheduled for first week of July 2011.
  • In the managerial coordination meeting, it is planned to discuss on the performance of DEC’s design activities and general coordination of the works and to find out all possible resolution.

Transmission Line
(GIII To Wolaita-Sodo Substation)

  • Gibe III-Wolaita Transmission Line (50.3 km double circuit 400kV, 3 phases and 51km single circuit 400kV) Construction Contract has been signed on July 24, 2009 with TBEA of China at a cost of USD 34 M of which 85% is to be covered by a loan from EXIM Bank of China.
  • TBEA Co.Ltd has submitted additional design documents/drawings to EEPCo for approval. The submitted documents/drawings are approved by EEPCo’s Transmission and Substation Engineering Office.
  • The contractor is preparing design for foundation.
  • The Loan Agreement for execution of the Gibe III-Wolaita-Addis Ababa 400kV Power Transmission Project (comprises substations and transmission lines) has been signed by MoFED and by EXIM Bank of China. The Loan Agreement has been also approved by the Council of Ministers and has been deliberated to the Ethiopian Parliament for its ratification. After review by Budget and Finance Standing Committee, the Parliament has approved the Loan Agreement on June 16, 2011.
  • For implementation of the project the Contractor has submitted the work schedule.
  • EEPCo’s delegates are attending tower test witnessing in China since June 6, 2011.
Environmental And Social Studies • Establishment of the Environmental and Social monitoring and Management Implementation Unit in Addis Ababa, at site and at Jinka has been completed.
• Four Environmental and Social monitoring Coordinators have been assigned at four woredas around Jinka (Dasenech,Nyagatom,Hammer and Selamago).They are mainly engaged in awareness creation works. • All ESIA related studies are completed. All the final ESIA and RAP reports are posted on EEPCo's Website as of March 5, 2009. Final report for archeological study has been submitted. The establishment of an office for the Environmental and Social monitoring and management sub process team at project level is completed. Preparation of project- based website is Completed. A mediation between the African Development Bank and Friends of Lake Turkana (FOLT) has been conducted on June 10 and 11, 2009, in Nairobi and the AfDB representatives have briefed EEPCo's management on the outcome. The FOLT has requested the bank for further studies to be conducted on the project, especially hydrological studies and public consultation on the Kenyan side. The Bank has accepted the request and engaged in finding consultants for the study.
• The first meeting of the Environmental Advisory panel has been held on 10 july 2008 and the members have received electronic copies of the ESIA studies documents. The Advisory panel members have conducted the first site visit from 31 st July 2009 to 02 August 2009 and held a meeting during the site visit. The EAP has been conducting a number of meetings and has prepared action plan for the Panel.
• Establishment of the Environmental and Social monitoring and Management Implementation Unit in Addis Ababa, at site and at Jinka Town(SNNP).
• Additional Public consultation has been done on December 2009 to February 2010 with upstream and downstream communities.

General
A joint mission from the AfDB, EIB and World Bank were in Ethiopia from October 10-20, 2009. The missions had visited the project site and consult the downstream communities. The missions also held different meetings with EEPCo and participated in the EFTA study Workshop conducted on oct-19-2009.


Plung Pool
The Contractor stopped the works waiting for the results of the hydraulic model test related to the depth of the invert of the plunge pool. In addition the quality of the rock is not good and the Contractor is waiting a new support design.


Chida-Sodo Road And Employer’s permanent camp
• On the left side of the river, the Contractor is doing clearing and levelling works of the road, so far 26.5 km has been done.
• on the right side of the river, the clearing and levelling works has been done up to a distance of 4km, The Contractor stopped the work on the right side as he has shifted the resources to the left side
• The Contractor has completed earth works and he is preparing a platform to commence the construction of the Employer's permanent camp
• The Contractor has commenced construction of EPC plant contractor's (DEC) camp.

Compensation Payments
• So far Compensation payment for the permanent camp area has been made for fifty three (53) peoples with a total of 3.87 Million Birr.
In total one hundred and sixty three (169) persons are compensated so far for Sodo-Chida road relocation and Employer's permanent camp with Birr 7.52M.
 
Chaajabu kipi apo....
Hata product ya somalia inaweza ikatusaidia nchi hii yamagamba....
Idiot Ccm
 
Mkuu CTOFU, Cha ajabu ni kwamba Nchi hii ina;
-Vyanzo vya maji(Maziwa, Mito, Maporomoko, mabwawa)
- Nishati ya Makaa ya Mawe
- Uwezo wa kutumia Upepo
- Gesi
- Vyura wa Kihansi
- Nguvu ya Jua, n.k

lakini bado tunaweza kudiriki kuomba Umeme(what's the difference btn now na wakati wa Uhuru)..to me naona kama sasa hivi tunauwezo mkubwa wa kuomba omba!

Mbona Jirani zetu(Kenya) wana vyanzo vichache sana vya Umeme yet they rely kwenye Hydropower na hisikii hata migao kama Tanzania?
 
Nchi yetu ni maskini wa kila kitu, kufiri hatakutumia rasilimali zetu! Sijui haka kaugonjwa kata isha lini?
 
mazuri hayo ,mnashangaa kununua umeme ethiopia tusishangae kwani serikali ya ethiopia ina mipango ya muda mfupi na mrefu inaosimamiwa kwa uadilifu na inapimwa kwa utekelezaji wa ufanisi,serikali haipangi kwa kupata political gains ambazo mara zote huwa za muda mfupi .vilevile katika mipango ya maendeleo kila kiongozi anakabidhiwa kwa dhamana ya utekelezaji ukiharibu unawajibishwa rushwa kubwa na ndogo haifumbiwi macho lakini kubwa zaidi uongozi wao ni kama team ya mpira inayotayarishwa kwa mechi za kombe la dunia, viongozi mbalimbali wakiwemo hata wetu huenda kushangaa maendeleo ya ethipia. la kuwanalo kama wazo la leo kila uamuzi huwa unasimamiwa sio kwa usanii bali kwa kipimo cha ufanisi .wazo la leo uongozi husema ethiopia first na mipango yote huelekezwa katika kufanikisha slogan hiyo ethiopia first .
 
Iv ili liliishia wap mana naona hadith na mbwembwe zinakuwa nyingi kuliko utekelezaj,Apa unaweza kuta alitoka confidently kabisa had kwenye vipind vya runinga akaongea lakin sijajua kinaendelea nn au bado upembuz yakinifu unaendelea maana hili neno hutumikag sana kuzima maswali kama haya.
 
4 Reactions
Reply
Back
Top Bottom