    TO EVERY ONE WHO CAN SOLVE THIS Question:

    A and B can do a piece of work in 21 days and 24 days respectively. They started the work together and after some days A leaves the work and B complete the remaining work in 9 days. After how many days did A leaves the work?


    Give the solution.